Aftout Es-Saheli Water Supply (Phase II) (US$8.4 million)
|
| Purpose |
| To boost water supplies in Nouakchott |
| Activities |
- construction of water intake facilities;
- construction of water treatment plants, pumping station and reservoir; and
- installation of water transmission pipes.
|
| Project cost |
| US$237.09 million |
| Co-financiers |
| AfDF, Arab Fund, IsDB, Kuwait Fund, Saudi Fund Government of Mauritania |
| Executing Agency |
| Ministry of Water Resources, Energy, Technologies of Information and Communication through the National Company of Water
|
| Implementation period |
| 3 years |