Cumulative Public Sector Loans as of December 16, 2008

Project Loans millions of US dollars
Agriculture & agro-industry 26.500
Education 6.500
Energy 22.300
Health -
Industry -
Multi-sectoral and other -
National Development Banks -
Telecommunications 8.000
Transportation 40.000
Water Supply & Sewerage 13.700
TOTAL 117.000

Recently Concluded Loan Agreements

For greater detail on the project/program or information on procurement opportunities, requests must be addressed directly to the executing agency (ies) of the project/program.

April 21, 2008
Rural Reconstruction and Rehabilitation (US$10 million)
Purpose:
To improve rehabilitation and construction of rural roads in 38 districts in in the western, central and eastern mountainous regions of Nepal.
Activities:
  • rehabilitation of infrastructure such as water supply and sanitation networks, irrigation schemes, schools and health posts;
  • implementation of community empowerment initiatives and institution strengthening measures;
  • upgrading of 825 km of rural roads and construction of bridges totaling 1,260 m; and
  • project management services.
Project cost:
US$104.7 million
Co-financiers:
AsDB, Governments of the United Kingdom and Nepal
Executing Agency:
Ministry of Local Development
Implementation period:
4 years

November 20, 2007
Road Connectivity (US$10 million)
Purpose:
To provide all-weather roads to communities in mountainous regions
Activities:
  • expansion and upgrading of 190 km of feeder roads;
  • provision of road markings and signs;
  • land acquisition and resettlement; and
  • consultancy services.
Project cost:
US$72.5 million
Co-financiers:
Asian Development Bank, Government of Nepal
Executing Agency:
Minstry of Physical Planning and Works
Implementation period:
6 years

BOP Support Loans millions of US dollars
TOTAL 4.15

Program Loans millions of US dollars
Commodity imports 5.000
TOTAL 5.000